Air Tightness Testing & New Buildings

Air Tightness Testing & New Buildings

Is Air Tightness Testing Mandatory on All New Buildings?

Yes, air tightness testing is a mandatory requirement for most new-build residential and commercial properties in England and Wales.

Since June 2022, changes to Part L of the Building Regulations have introduced stricter air tightness testing requirements. The aim is to ensure new buildings are properly sealed, energy efficient, and meet the required air permeability standards.

Previously, developers could use sample testing on certain residential developments, meaning only a percentage of new homes needed testing. Unfortunately, this approach sometimes meant that properties with poor airtightness could go undetected.

The updated regulations have made the requirements much clearer, with air testing now required for every new dwelling rather than relying on sample testing.

Get an Air Tightness Testing Quote ▶

What Are the New Mandatory Air Tightness Testing Requirements?

The updated ATTMA Technical Standard L1 (TSL1) has simplified the testing process and made the requirements easier to understand.

Under the updated Part L Building Regulations, developers and builders must pay closer attention to their buildings’ airtightness. This applies to individual houses, apartments and relevant commercial developments.

The main changes include:

  1. All new dwellings must be air-tested. Every new house and apartment must undergo an airtightness test, regardless of the development’s size.
  2. Commercial buildings must be tested. Relevant new commercial buildings must also undergo air permeability testing to demonstrate compliance with Part L.
  3. Stricter air leakage targets. The previous limiting air permeability value of 10m³/hr/m² at 50Pa was reduced to 8m³/hr/m² at 50Pa.
  4. Equipment calibration requirements. Testing equipment must be maintained and calibrated in accordance with the applicable standards and manufacturer requirements.

These changes have removed much of the uncertainty surrounding sample testing and placed greater emphasis on the airtightness performance of individual buildings.

How Many Buildings Need a Blower Door Test?

One of the biggest changes introduced by the updated Part L regulations is the requirement to test every new dwelling.

Previously, certain developments could use sample testing, meaning only a selection of properties needed to undergo an airtightness test. This is no longer the approach for new dwellings under the updated requirements.

Moving forward, builders and developers should allow for air tightness testing on every new house and apartment.

The requirements also extend to relevant new commercial buildings and certain extensions that are treated as new buildings under Part L.

Air tightness testing, also known as blower door testing or air permeability testing, measures how much air escapes through gaps and cracks in a building’s structure. The results are then used as part of the SAP or SBEM compliance process to demonstrate that the building meets its designed air permeability target.

More Mandatory Testing Under Part L

The updated Approved Document L has made air testing requirements more straightforward.

For residential developments, every new dwelling must be tested rather than relying on the previous sampling approach.

For non-residential buildings, testing requirements depend on the building type and the applicable Part L provisions. Where an air permeability test is required, the building must demonstrate that it achieves the specified design target.

This means developers need to consider air tightness testing much earlier in the construction process and allow sufficient time for testing before completion and handover.

Changes to Air Testing Equipment Calibration

Another important consideration is calibrating and maintaining air testing equipment.

Testing equipment must be properly calibrated to ensure accurate, reliable results. Testing companies should follow the relevant ATTMA requirements and the equipment manufacturer’s recommendations.

Keeping equipment properly maintained and calibrated is essential to ensuring that air tightness test results are accurate and suitable for Building Regulations compliance.

When Should I Arrange an Air Tightness Test?

You should normally arrange an air tightness test once the building is substantially complete and ready for testing.

Before booking your test, there are a few important things to check:

  • All external doors and windows should be fitted.
  • Install internal doors where required.
  • Floor finishes and ceilings should be complete.
  • Service penetrations through walls and floors should be properly sealed.
  • Extractor fans, ventilation openings and other relevant gaps should be prepared in accordance with the testing standard.
  • You should have your designed air permeability target available.

You can usually find your designed air permeability target in the design-stage SAP assessment for residential properties or the relevant SBEM assessment for commercial buildings.

You need this figure before arranging your test, as it determines the air leakage rate your building must achieve.

Should I Arrange More Than One Airtightness Test?

If your project has a particularly demanding airtightness target, it can be worth arranging an initial test before the building is fully finished.

For example, if you are aiming for an air leakage result below 3m³/hr/m² at 50Pa, an early test can help identify any significant air leakage problems before they become difficult or expensive to resolve.

A typical approach would be:

  1. Initial air test: Carried out once the building’s main structure and airtightness layer are complete. This helps identify leaks around windows, doors, service penetrations and other potential problem areas.
  2. Final air test: Carried out once the remaining construction work is finished, to establish the building’s final air permeability result.

Although an early test is not always necessary, it can save considerable time and money on projects where achieving a particularly low air leakage rate is important.

About APT Sound Testing – Mandatory Air Tightness Testing

APT Sound Testing provides professional air tightness testing services for residential and commercial developments throughout the UK.

Air tightness testing, also referred to as air permeability testing or blower door testing, is an important part of demonstrating compliance with Part L of the Building Regulations.

As an experienced testing company, we have carried out thousands of tests for house builders, property developers, self-builders, architects and housing associations.

Our engineers use calibrated testing equipment and follow the relevant testing standards to measure air leakage accurately and provide the results needed for Building Regulations compliance.

We also understand that identifying air leakage problems can be challenging, particularly on larger developments. That’s why we can offer practical advice on common leakage areas and help clients understand where improvements may be needed.

Whether you need a test for a single new-build house, an apartment block, a commercial unit or a large residential development, we can provide a reliable service with competitive prices and nationwide coverage.

Preparing Your Building for an AAirtightnessTest

Good preparation is essential if you want your building to pass its airtightness test the first time.

Small gaps around windows, doors, service penetrations, pipework and ventilation openings can all contribute to excessive air leakage.

To help you prepare, we’ve put together an airtightness testing checklist covering the main areas to check before your engineer arrives.

Download Our Air Tightness Testing Checklist ▶


Contact APT Sound Testing for Mandatory Air Tightness Testing

Do you need to arrange an air tightness test for a new residential or commercial development?

APT Sound Testing can help you meet your Part L testing requirements with a professional, reliable and competitively priced service.

Our experienced team can arrange testing at short notice, subject to availability, and provide practical advice to help keep your project on track.

APT Sound Testing Ltd

☎ Office: 01525 303905

☎ Mobile: 07775623464

✉ Email: info@aptsoundtesting.co.uk

🌐 Website: www.aptsoundtesting.co.uk